DODGE RAM 1500 1998 2.G Workshop Manual (d) Compress first spring with flat blade screw-
driver and slide strut into position in hub slot.
Then work spring into seat in strut with small
hooked tool or screwdriver.
(e) Install second and thi

Page 1777 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (39) Roll gear case onto its left side.
(40) Grip mainshaft at pilot bearing hub and just
behind reverse gear. Then lift assembly and guide
rear of shaft through bearing bore at rear of case.
(41) Con

Page 1778 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (5) Install new oil seal in front bearing retainer
with Installer 6052 (Fig. 112). Use one or two wood
blocks to support retainer as shown. Lubricate seal
lip with petroleum jelly after installation.

Page 1779 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (12) Install mainshaft fifth gear with Installer
6446 (Fig. 116). Gear is seated when it contacts rear
bearing.
COUNTERSHAFT FIFTH GEAR SYNCHRO
(1) Install thrust washer pin in countershaft (Fig.
117)

Page 1780 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (4) Install synchro sleeve on hub of countershaft
fifth gear with tapered side of sleeve facing front and
the flat side facing rear (Fig. 120).
(5) Install shift fork in synchro sleeve (Fig. 121).(6)

Page 1781 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (8) Assemble and install fifth synchro clutch gear
and stop ring in fifth gear hub (Fig. 124). Verify
parts are seated in fifth gear hub.
(9) Install clutch gear snap ring (Fig. 125).
(10) Align roll

Page 1782 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (10) Tighten fifth gear nut with Nut Wrench 6743
and high capacity torque wrench. Tighten nut to 366-
380 N´m (270-280 ft. lbs.). Have helper hold trans-
mission steady if necessary.
(11) Torque the

Page 1783 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual INSTALLATION
NOTE: If a new transmission is being installed, use all
components supplied with the new transmission. For
example, if a new shift tower is supplied with the new
transmission, do not re-u

Page 1784 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual SPECIFICATIONS
TORQUE SPECIFICATIONS
DESCRIPTION N´m Ft. Lbs. In. Lbs.
Switch, Back-up Lamp 22-34 16-25 -
Countershaft Bearing Plate Bolts 19-26 14-19 170-230
Fifth Gear Nut 366-380 270-280 -
Fifth G

Page 1785 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual INSTALLER SEAL C-3972-A
INSTALLER SEAL 8154
INSTALLER SEAL C-3860-A
WRENCH 6443