INJECTION
CHECKS: LOW PRESSURE FUEL SUPPLY CIRCUIT
Checks on pressure: dynamic.
Engine running, at idle (normal functioning):
- Fuel supply pressure shown by the pressure gauge [3] = 2 ± 0.4 bar.
- Fuel return pressure shown by the pressure gauge [3] = 0.7 ± 0.4 bar.
Abnormal functioning
Fuel supply pressure Fuel return pressure Checks
Between 3and 3.5bar0.7 ± 0.2 bar Check the condition of the diesel filter
More than 3.5bar Less than 0.7barCheck the low pressure regulator incorporated
in the filter
(locked shut): replace.
More than 3.5bar More than 0.7barCheck the fuel return circuit
(pipe pinched or trapped…)
Between 0.8and 1.5bar Less than 0.7barCheck the fuel supply circuit:
- Booster pump (low pressure), piping
Impossible to start the engine:Check: diesel injector return flow
(table below).Fuel supply pressure less than 0.8 bar:
- Check the low pressure regulator incorporated in the filter (locked open).- Check the high pressure pump distribution valve (locked shut).Uncouple the diesel injector return pipe.
Check: Observe:
The flow should be drop by drop Diesel injector functioning correctly
Excessive fuel return Diesel injector locked shutEngines: RHY - RHZ (continued)
XSARA PICASSO
Angl.-t2-page283-305-2005 9/01/06 10:18 Page 289
Page 302 of 462
![Citroen BERLINGO 2005 1.G Workshop Manual Downloaded from www.Manualslib.com manuals search engine 296
INJECTION
CHECKING THE AIR SUPPLY CIRCUIT
Tool.
[1]Manual pressure-vacuum pump: FACOM DA 16
Vacuum pump:
- Connect the tool [1]onto the va Citroen BERLINGO 2005 1.G Workshop Manual Downloaded from www.Manualslib.com manuals search engine 296
INJECTION
CHECKING THE AIR SUPPLY CIRCUIT
Tool.
[1]Manual pressure-vacuum pump: FACOM DA 16
Vacuum pump:
- Connect the tool [1]onto the va](/img/9/4138/w960_4138-301.png)
Downloaded from www.Manualslib.com manuals search engine 296
INJECTION
CHECKING THE AIR SUPPLY CIRCUIT
Tool.
[1]Manual pressure-vacuum pump: FACOM DA 16
Vacuum pump:
- Connect the tool [1]onto the vacuum pump (1).
- Start the engine.
- Wait 30 seconds.
The vacuum value should be 0.9 ± 0.1 barat idle.
B1HP1K8D
Engines: 8HX - 8HZ
XSARA
Angl.-t2-page283-305-2005 9/01/06 10:18 Page 296
Page 303 of 462
![Citroen BERLINGO 2005 1.G Workshop Manual Downloaded from www.Manualslib.com manuals search engine 297
INJECTION
CHECKING THE AIR SUPPLY CIRCUIT
Tool.
[1]Manual pressure-vacuum pump: FACOM DA 16
Checks.
Vacuum pump.
Connect the tool [1]into t Citroen BERLINGO 2005 1.G Workshop Manual Downloaded from www.Manualslib.com manuals search engine 297
INJECTION
CHECKING THE AIR SUPPLY CIRCUIT
Tool.
[1]Manual pressure-vacuum pump: FACOM DA 16
Checks.
Vacuum pump.
Connect the tool [1]into t](/img/9/4138/w960_4138-302.png)
Downloaded from www.Manualslib.com manuals search engine 297
INJECTION
CHECKING THE AIR SUPPLY CIRCUIT
Tool.
[1]Manual pressure-vacuum pump: FACOM DA 16
Checks.
Vacuum pump.
Connect the tool [1]into the vacuum pump (1).
Start the engine.
The vacuum value should be 0.9 ± 0.1 barat idle
(after 30 secondsof operation).
NOTE:The exhaust gas recycling valve is not linked to the air supply circuit.
The exhaust gas recycling electrovalve is controlled by the engine ECU.
Turbocharging pressure regulation valve.
Connect the tool [1]on the valve (2).
Apply a vacuum of approx. 0.8 bar.
Rod "a"should move 6 ± 2 mm.B1HP1UGC
B1HP22RC
Engine: 9HX
C4
Angl.-t2-page283-305-2005 9/01/06 10:18 Page 297
Page 304 of 462
![Citroen BERLINGO 2005 1.G Workshop Manual Downloaded from www.Manualslib.com manuals search engine 298
INJECTION
CHECKING THE AIR SUPPLY CIRCUIT
Tool.
[1]Manual pressure-vacuum pump: FACOM DA 16
Checks.
Vacuum pump.
Connect the tool [1]into t Citroen BERLINGO 2005 1.G Workshop Manual Downloaded from www.Manualslib.com manuals search engine 298
INJECTION
CHECKING THE AIR SUPPLY CIRCUIT
Tool.
[1]Manual pressure-vacuum pump: FACOM DA 16
Checks.
Vacuum pump.
Connect the tool [1]into t](/img/9/4138/w960_4138-303.png)
Downloaded from www.Manualslib.com manuals search engine 298
INJECTION
CHECKING THE AIR SUPPLY CIRCUIT
Tool.
[1]Manual pressure-vacuum pump: FACOM DA 16
Checks.
Vacuum pump.
Connect the tool [1]into the vacuum pump (1).
Start the engine.
Wait 30 seconds.
The vacuum value should be 0.9 ± 0.1 barat idle.
NOTE:The exhaust gas recycling valve is not linked to the air supply circuit.
The exhaust gas recycling electrovalve is controlled by the engine ECU.
Turbocharging pressure regulation valve.
Connect the tool [1]on the valve (2)
(tube identified by the colour grey).
Apply a vacuum of approx. 0.8 bar.
Rod "a"should move 12 ± 2 mm.
B1HP1UGC
B1HP1UHC
Engines: 9HY - 9HZ
C4
Angl.-t2-page283-305-2005 9/01/06 10:18 Page 298
Page 378 of 462

Downloaded from www.Manualslib.com manuals search engine 372
AXLES
SUSPENSION
STEERING
CHECKING THE POWER STEERING ASSISTANCE PRESSURE
Preliminary operation.
Move aside the high pressure pipe (1).
Do up:
- The union [6]on the power steering electropump.
- The union [7]on the high pressure pipe (1).
- Tighten all the unions.
Fill the power steering reservoir 10 mmabove the max. level.
IMPERATIVE: Use new power steering fluid for both filling and topping-up the circuit.
Open the tap [5].
Start the engine and allow it to run for 5 seconds.
Stop the engine.
Move the steering several timesin each direction.
Check the steering fluid level and make sure that there are no leaks.
Checking the electropump pressure.
Start the engine.
Close the tap [5]for 5 seconds.
Open the tap [5].
Stop the engine.
At accelerated idle
(1200 to 1500rpm), the pressure should be 105 ± 5 bars.
If the electropump pressure is correct, check the valve sealing.
B3EP16EC
C4
Angl.-t2-page361-397-2005 9/01/06 10:22 Page 372
Page 379 of 462

Downloaded from www.Manualslib.com manuals search engine 373
AXLES
SUSPENSION
STEERING
CHECKING THE POWER STEERING ASSISTANCE PRESSURE
Checking the valve sealing.
Remove the under-engine shield.
Move aside the heat shield from the steering mechanism.
Slacken the unions (2)on the power steering ram.
Uncouple the two supply pipes (3)from the distributor valve and move them aside.
Fit on the distributor valve the two plugs [8], tighten to 0,8 m.daN.
Move the steering slowly from lock to lock, to drain the ram.
Top up the level of the power steering fluid.
Open the tap [5].
Stop the engine.
Maintain the engine speed at accelerated idle.
Hold the wheels on full lock, first on one side then on the other.
The pressure should adjust to 105 ± 5 bars.
The pressure is correct: replace the steering mechanism.
The pressure is lower than the values above: replace the distributor valve.
Couple the two supply pipes (3)on the distributor valve; tighten to 0,8 m.daN.
Retighten the unions (2)on the power steering ram; tighten to 0,8 m.daN.
Remove the union [7]on the high pressure pipe (1)and the union [6]on the power steering
electropump.
Refit:
- the high pressure pipe (1); tighten to 2 ± 0,2 m.daN.
- the screen wash reservoir, the front RH splash-shield and the front RH wheel.
B3EP16FC
B3EP16GC
C4
Angl.-t2-page361-397-2005 9/01/06 10:22 Page 373
Page 380 of 462

Downloaded from www.Manualslib.com manuals search engine AXLES
SUSPENSION
STEERING
CHECKING THE POWER STEERING ASSISTANCE PRESSURE
Fill the power steering reservoir to the max.mark «a»on the cap (4).
Engine stopped, move the steering slowly from lock to lock, in both directions approx. ten times.
Top up the fluid to the max. mark «a»on the cap (4).
Run the engine at idle for 3 minutes, without any action on the steering wheel.
Move the steering from lock to lock, until there is no longer any tight spot.
Top up the level if it again goes down.
Bleed the circuit by moving the steering several timesin each direction.
Top up the level if it again goes down.
IMPERATIVE: Use new power steering fluid for both filling and topping-up the circuit.
B3EP16HC
374
C4