engine DODGE RAM 2001 Service Repair Manual
[x] Cancel search | Manufacturer: DODGE, Model Year: 2001, Model line: RAM, Model: DODGE RAM 2001Pages: 2889, PDF Size: 68.07 MB
Page 1729 of 2889

A leak at the front of the transmission will be from
either the front bearing retainer or retainer seal.
Lubricant may be seen dripping from the clutch
housing after extended operation. If the leak is
severe, it may also contaminate the clutch disc caus-
ing the disc to slip, grab and or chatter.
A correct lubricant level check can only be made
when the vehicle is level. Also allow the lubricant to
settle for a minute or so before checking. These rec-
ommendations will ensure an accurate check and
avoid an underfill or overfill condition. Always check
the lubricant level after any addition of fluid to avoid
an incorrect lubricant level condition.
HARD SHIFTING
Hard shifting is usually caused by a low lubricant
level, improper or contaminated lubricants. The con-
sequence of using non-recommended lubricants is
noise, excessive wear, internal bind and hard shift-
ing. Substantial lubricant leaks can result in gear,
shift rail, synchro, and bearing damage. If a leak
goes undetected for an extended period, the first indi-
cations of component damage are usually hard shift-
ing and noise.
Component damage, incorrect clutch adjustment or
damaged clutch pressure plate or disc are additional
probable causes of increased shift effort. Incorrect
adjustment or a worn/damaged pressure plate or disc
can cause incorrect release. If clutch problem is
advanced, gear clash during shifts can result. Worn
or damaged synchro rings can cause gear clash when
shifting into any forward gear. In some new or
rebuilt transmissions, new synchro rings may tend to
stick slightly causing hard or noisy shifts. In most
cases this condition will decline as the rings wear-in.
TRANSMISSION NOISE
Most manual transmissions make some noise dur-
ing normal operation. Rotating gears generate a mild
whine that is audible, but generally only at extreme
speeds.
Severe highly audible transmission noise is gener-
ally the initial indicator of a lubricant problem.
Insufficient, improper or contaminated lubricant will
promote rapid wear of gears, synchros, shift rails,
forks and bearings. The overheating caused by a
lubricant problem, can also lead to gear breakage.
REMOVAL
NOTE: Use a heavy duty scissors style transmis-
sion jack for remove of the transmission.
(1) Disconnect battery negative cable.
(2) Shift transmission into Neutral.
(3) Remove screws attaching shift boot to floorpan.
Then slide boot upward on the shift lever.(4) Remove the bolts holding the shift tower to the
isolator plate and transmission gear case.
(5) Remove the shift tower and isolator plate from
the transmission gear case.
(6) Raise and support vehicle.
(7) Remove skid plate, if equipped.
(8) Mark propeller shaft/shafts and axle yokes for
installation reference.
(9) Remove propeller shaft.
(10) Disconnect and remove exhaust system as
necessary.
(11) Disconnect wires at backup light switch.
(12) Support engine with adjustable safety stand
and wood block.
(13) If transmission is to be disassembled for
repair, remove drain bolt at bottom of PTO cover and
drain lubricant from transmission (Fig. 4).
(14) Remove clutch slave cylinder splash shield, if
equipped.
(15) Remove clutch slave cylinder bolts and move
cylinder aside for clearance.
(16) Remove wire harness from clips on transmis-
sion.
TWO WHEEL DRIVE
(1) Remove bolts/nuts mounting transmission to
the rear mount.
(2) Support and secure transmission with safety
chains to a transmission jack.
(3) Remove rear crossmember.
(4) Remove transmission clutch housing bolts at
the engine block.
(5) Slide transmission and jack rearward until
input shaft clears clutch disc and pressure plate.
(6) Lower transmission jack and remove transmis-
sion from under vehicle.
Fig. 4 NV5600 Drain Bolt
1 - PTO COVER
2 - DRAIN BOLT
21 - 94 MANUAL - NV5600BR/BE
MANUAL - NV5600 (Continued)
Page 1730 of 2889

FOUR WHEEL DRIVE
(1) Disconnect transfer case shift linkage at trans-
fer case range lever.
(2) Support and secure transfer case with safety
chains to a transmission jack.
(3) Remove transfer case mounting nuts.
(4) Move transfer case rearward until input gear
clears transmission mainshaft.
(5) Lower transfer case assembly and move it from
under vehicle.
(6) Support and secure transmission with safety
chains to a transmission jack.
(7) Remove bolts/nuts attaching transmission
mount to rear crossmember.
(8) Remove rear crossmember.
(9) Remove transmission clutch housing bolts at
the engine block.
(10) Move transmission rearward until input shaft
clears clutch disc.
(11) Lower transmission and remove it from under
vehicle.
DISASSEMBLY
NOTE: The use of Fixture 8241 for moving and han-
dling the NV5600 is required. The fixture supports
the transmission at the center of gravity in order to
ease mounting the transmission into the build fix-
ture.
(1) Using Fixture 8241, mount the transmission
into the Build Fixture 8230 (Fig. 5).
(2) Rotate the transmission to the horizontal posi-
tion, if necessary.
(3) Remove the shift tower (Fig. 6) and isolator
plate (Fig. 7).
(4) Remove primary shift rail detent plug (Fig. 8).
(5) Remove primary shift rail detent spring (Fig.
9).
(6) Remove primary shift rail detent plunger (Fig.
10).
(7) Remove clutch housing bolts (10) (Fig. 11) from
inside the housing.
(8) Remove shift rail blocker bolt (Fig. 12) from the
side of the transmission gear case.
Fig. 5 TRANSMISSION BUILD FIXTURE
1 - FIXTURE
2 - TRANSMISSION
Fig. 6 Shift Tower
1 - SHIFT TOWER
2 - TRANSMISSION
BR/BEMANUAL - NV5600 21 - 95
MANUAL - NV5600 (Continued)
Page 1736 of 2889

TRANSMISSION GEAR CASE
(1) Remove remaining bolts holding the transmis-
sion gear case to the clutch housing.
(2) Remove the shift socket roll pin with a 6mm
(7/32 inch) punch and hammer.(3) Install Fixture 8232 to the transmission gear
case.
(4) Attach an engine crane or equivalent to Fixture
8232 and remove the transmission gear case from the
clutch housing (Fig. 27).
(5) Remove rear output shaft and countershaft
bearing races from the transmission gear case with a
brass drift and hammer.
GEARTRAIN
(1) Remove bolts holding the 5-6 crossover bracket
to the clutch housing (Fig. 28).
(2) Attach Fixture 8232 to the output shaft and
countershaft (Fig. 29).
(3) Attach an engine crane or equivalent to Fixture
8232 and raise the geartrain approximately 1/4 in.
from the clutch housing.
(4) Remove 5-6 crossover bracket from the clutch
housing.
(5) Lower the geartrain back into the clutch hous-
ing.
(6) Install Holding Tool 8242 (Fig. 30) onto the 5-6
synchro and tighten the screw to hold the 5-6 syn-
chro together during the removal operation.
NOTE: Pay attention to the order of the shift fork
arms at the primary shift rail when they are in the
Neutral position.
Fig. 25 REVERSE BEARING SLEEVE
1 - REVERSE GEAR BEARING SLEEVE
Fig. 26 REVERSE SHIFT FORK
1 - REVERSE SYNCHRO
2 - REVERSE SHIFT FORK
Fig. 27 TRANSMISSION LIFT
1 - FIXTURE 8232
2 - TRANSMISSION CASE
BR/BEMANUAL - NV5600 21 - 101
MANUAL - NV5600 (Continued)
Page 1738 of 2889

(10) Remove geartrain from the clutch housing and
install the geartrain into Support Stand 8246 (Fig.
32).
(11) Remove Fixture 8232 from the output shaft
and the countershaft.
(12) Separate the countershaft from the output
shaft.
(13) Separate the output shaft from the input
shaft. Hold the 5-6 synchro together while removing
the output shaft to prevent the synchro sleeve from
being dislodged from the synchro hub.
COUNTERSHAFT BEARINGS
(1) Remove snap-ring holding the front counter-
shaft bearing onto the countershaft.
(2) Remove front countershaft bearing with Sleeve
6444-8, Adapters 6451, Puller Rods 6444-4 and Puller
6444 (Fig. 33).
(3) Remove rear countershaft bearing with Sleeve
6444-8, Adapters 6447, Puller Rods 6444-4, Puller
6444 and suitable press button (Fig. 34).
Fig. 32 LIFT GEARTRAIN WITH ENGINE CRANE
1 - FIXTURE 8232
2 - SUPPORT STAND 8246
Fig. 33 FRONT COUNTERSHAFT BEARING
1 - PULLER 6444
2 - ADAPTERS 6451
Fig. 34 REAR COUNTERSHAFT BEARING
1 - PULLER 6444
2 - ADAPTERS 6447
BR/BEMANUAL - NV5600 21 - 103
MANUAL - NV5600 (Continued)
Page 1754 of 2889

GEARTRAIN
(1) Install input shaft into Support Stand 8246.
(2) Install fifth gear friction cone onto the input
shaft.
(3) Install fifth gear blocker ring onto the fifth
gear friction cone.
(4) Install output shaft into the input shaft (Fig.
79).
(5) Install countershaft into the Support Stand
8246 and verify that all gears are meshed with their
mates on the mainshaft (Fig. 80).
(6) Install Fixture 8232 to the output shaft and
the countershaft.
(7) Install Holding Tool 8242 onto the 5-6 synchro
and tighten the screw to hold the 5±6 synchro
together during the remainder of the installation pro-
cedure.(8) Attach and engine crane or equivalent to Fix-
ture 8232 and move the geartrain from the Support
Stand 8246 to the clutch housing (Fig. 81).
(9) Install shift forks and rails onto the geartrain
(Fig. 82).
NOTE: The closest shift arm to the geartrain is for
Reverse. The next is 5-6, then 3-4 and then 1-2
when moving out from the geartrain.
(10) Install geartrain and shift rails into the clutch
housing. Lower the geartrain and rails into the hous-
ing slowly while guiding input shaft through input
shaft seal. Avoid any binds on the shift rails, forks
and synchros as the rails enter their bushings.
CAUTION: Do not damage input shaft seal with the
input shaft splines.
Fig. 79 Install Output Shaft to Input Shaft
1 - OUTPUT SHAFT
2 - INPUT SHAFT
3 - SUPPORT STAND 8246
Fig. 80 Countershaft to Mainshaft
1 - COUNTERSHAFT
2 - OUTPUT SHAFT
3 - SUPPORT STAND 8246
BR/BEMANUAL - NV5600 21 - 119
MANUAL - NV5600 (Continued)
Page 1755 of 2889

(11) With the geartrain approximately 1/4 in. from
the clutch housing, remove Holding Tool 8242 from
the 5-6 synchro (Fig. 83).
(12) Install 5-6 crossover bracket and arm to the
shift rails and the clutch housing.(13) Lower geartrain the remainder of the way
into the clutch housing.
(14) Install the 5-6 crossover bracket bolts (Fig.
84).
(15) Remove engine crane and Fixture 8232 from
the output shaft and the countershaft.
Fig. 81 Lift Geartrain with Engine Crane
1 - FIXTURE 8232
2 - SUPPORT STAND 8246
Fig. 82 Install Shift Rails
1 - SHIFT RAILS
Fig. 83 Holding Tool 8242
1 - HOLDING TOOL 8242
2 - 5-6 SYNCHRO
Fig. 84 5-6 Crossover Bracket Bolts
1 - 5-6 CROSSOVER BRACKET
21 - 120 MANUAL - NV5600BR/BE
MANUAL - NV5600 (Continued)
Page 1756 of 2889

TRANSMISSION GEAR CASE
(1) Install rear output shaft bearing race into the
transmission gear case with Installer C-4308 and
Handle C-4171.
(2) Install rear countershaft bearing race into the
transmission gear case with Installer 8153 and Han-
dle C-4171.
(3) Install Fixture 8232 to the transmission gear
case.
NOTE: Shift socket must be loose on the shift shaft
and is rotated a minimum of 90É from its normal
position. This will ensure enough clearance to
install the transmission gear case.
(4) Attach an engine crane or equivalent to Fixture
8232 and install the transmission gear case onto the
clutch housing (Fig. 85).
(5) Install clutch housing bolts and tighten to 48
N´m (35 ft.lbs.).
(6) Install shift socket roll pin with a suitable
6mm (7/32 inch) punch and hammer.MAINSHAFT AND COUNTERSHAFT ENDPLAY
(1) With transmission in vertical position, use
Socket 6993 to rotate the shafts and seat the bear-
ings.
(2) Measure mainshaft endplay with Dial Indicator
Set C-3339 and Extension Rod 8161 installed onto
the rear of the transmission gear case (Fig. 86).
(3) Measure countershaft end-play with Dial Indi-
cator Set C-3339 and Extension Rod 8161 installed
onto the rear of the transmission gear case (Fig. 87).
(4) Rotate transmission into a horizontal position
and remove the input shaft retainer.
(5) Install shims necessary to achieve an end-play
of 0.051-0.15 mm (0.002-0.006 in.) for the mainshaft
and countershaft.
NOTE: Countershaft shims go between the bearing
race and spacer. Mainshaft shims go into the input
shaft retainer.
Fig. 85 Transmission Gear Case
1 - FIXTURE 8232
2 - TRANSMISSION CASE
Fig. 86 Measure Mainshaft End-Play
1 - DIAL INDICATOR C-3339
2 - EXTENSION ROD 8161
3 - MAIN SHAFT
BR/BEMANUAL - NV5600 21 - 121
MANUAL - NV5600 (Continued)
Page 1760 of 2889

(18) Install crossover detent plunger, spring and
plug into the extension/adapter housing. Tighten the
plug to 47.5 N´m (35 ft.lbs.) (Fig. 97).
(19) Apply sealer to the surface of the transmis-
sion case.
(20) Install extension/adapter housing onto the
transmission case.
(21) Install bolts to hold the extension/adapter
housing onto the transmission gear case. Tighten
bolts to 48 N´m (35 ft.lbs.).
(22) Install shift rail blocker bolt and tighten bolt
to 55 N´m (41 ft.lbs.).
(23) Install primary shift rail detent plunger,
spring and plug into the transmission case. Tighten
detent plug to 47.5 N´m (35 ft.lbs.).(24) Install shift tower onto the transmission case
and tighten bolts to 9 N´m (7 ft.lbs.).
INSTALLATION
NOTE: If a new transmission is being installed, be
sure to use all components supplied with the new
transmission. For example, if a new shift tower is
supplied with the new transmission, do not re-use
the original shift tower.
NOTE: Use a heavy duty scissors style transmis-
sion jack to install the transmission.
Before installation apply light coat of Mopar high
temperature bearing grease to contact surfaces of fol-
lowing components:
²input shaft splines.
²release bearing slide surface of front retainer.
²release bearing bore.
²release fork.
²release fork ball stud.
²propeller shaft slip yoke.
(1) Apply sealer to threads of bottom PTO cover
bolt and install bolt in case.
(2) Mount transmission on jack and position trans-
mission under vehicle.
(3) Raise transmission until input shaft is centered
in clutch disc hub.
(4) Move transmission forward and start input
shaft in clutch disc and pilot bushing/bearing.
(5) Work transmission forward until seated against
engine block. Do not allow transmission to remain
unsupported after input shaft has entered clutch
disc.
(6) Install and tighten transmission-to-engine
block bolts.
(7) Install clutch slave cylinder.
(8) Connect backup light switch wires.
(9) Fill transmission with recommended lubricant.
Correct fill level is bottom edge of fill plug hole.
(10) Position transmission harness wires in clips
on transmission.
(11) Install transmission mount on transmission or
rear crossmember.
(12) Install rear crossmember.
(13) Remove transmission jack and engine support
fixture.
TWO WHEEL DRIVE
(1) Install propeller shaft with referece marks
aligned.
(2) Install exhaust system components.
(3) Remove support and lower vehicle.
(4) Shift transmission into third gear.
Fig. 96 Crossover Cam
1 - CROSSOVER CAM
2 - BOLT
3 - EXTENSION HOUSING
Fig. 97 Crossover Cam Detent Plug
1 - DETENT PLUG
2 - EXTENSION HOUSING
BR/BEMANUAL - NV5600 21 - 125
MANUAL - NV5600 (Continued)
Page 1770 of 2889

OVERRUNNING CLUTCH CAM/OVERDRIVE
PISTON RETAINER
DESCRIPTION..........................235
OPERATION............................235
DISASSEMBLY..........................235
CLEANING.............................236
INSPECTION...........................236
ASSEMBLY............................236
PARK/NEUTRAL POSITION SWITCH
DIAGNOSIS AND TESTING................237
PARK/NEUTRAL POSITION SWITCH.......237
REMOVAL.............................238
INSTALLATION..........................238
PISTONS
DESCRIPTION..........................238
OPERATION............................238
PLANETARY GEARTRAIN/OUTPUT SHAFT
DESCRIPTION..........................240
OPERATION............................240
DISASSEMBLY..........................240
INSPECTION...........................241
ASSEMBLY............................241
REAR CLUTCH
DESCRIPTION..........................246
OPERATION............................246
DISASSEMBLY..........................247
CLEANING.............................247
INSPECTION...........................248
ASSEMBLY............................248
REAR SERVO
DESCRIPTION..........................250
OPERATION............................250
DISASSEMBLY..........................251
CLEANING.............................251
ASSEMBLY............................251
SHIFT MECHANISM
DESCRIPTION..........................251OPERATION............................251
ADJUSTMENTS.........................252
SOLENOID
DESCRIPTION..........................252
OPERATION............................253
SPEED SENSOR
DESCRIPTION..........................253
OPERATION............................253
THROTTLE VALVE CABLE
DESCRIPTION..........................253
ADJUSTMENTS.........................254
TORQUE CONVERTER
DESCRIPTION..........................256
OPERATION............................260
REMOVAL.............................261
INSTALLATION..........................261
TORQUE CONVERTER DRAINBACK VALVE
DESCRIPTION..........................262
OPERATION............................262
STANDARD PROCEDURE.................262
TORQUE CONVERTER DRAINBACK VALVE . 262
TRANSMISSION TEMPERATURE SENSOR
DESCRIPTION..........................262
OPERATION............................262
VALVE BODY
DESCRIPTION..........................263
OPERATION............................267
REMOVAL.............................281
DISASSEMBLY..........................282
CLEANING.............................293
INSPECTION...........................293
ASSEMBLY............................294
INSTALLATION..........................303
ADJUSTMENTS.........................304
AUTOMATIC TRANSMISSION -
42RE
DESCRIPTION
The 42RE is a four speed fully automatic transmis-
sion (Fig. 1) with an electronic governor. The 42RE is
equipped with a lock-up clutch in the torque con-
verter. First through third gear ranges are provided
by the clutches, bands, overrunning clutch, and plan-
etary gear sets in the transmission. Fourth gear
range is provided by the overdrive unit that contains
an overdrive clutch, direct clutch, planetary gear set,
and overrunning clutch.
The transmission contains a front, rear, and direct
clutch which function as the input driving compo-
nents. It also contains the kickdown (front) and thelow/reverse (rear) bands which, along with the over-
running clutch and overdrive clutch, serve as the
holding components. The driving and holding compo-
nents combine to select the necessary planetary gear
components, in the front, rear, or overdrive planetary
gear set, transfer the engine power from the input
shaft through to the output shaft.
The valve body is mounted to the lower side of the
transmission and contains the valves to control pres-
sure regulation, fluid flow control, and clutch/band
application. The oil pump is mounted at the front of
the transmission and is driven by the torque con-
verter hub. The pump supplies the oil pressure nec-
essary for clutch/band actuation and transmission
lubrication.
BR/BEAUTOMATIC TRANSMISSION - 42RE 21 - 135
Page 1772 of 2889

IDENTIFICATION
Transmission identification numbers are stamped
on the left side of the case just above the oil pan gas-
ket surface (Fig. 2). Refer to this information when
ordering replacement parts.
GEAR RATIOS The 42RE gear ratios are:
1st.................................2.74:1
2nd................................1.54:1
3rd.................................1.00:1
4th.................................0.69:1
Rev.................................2.21:1
OPERATION
The application of each driving or holding compo-
nent is controlled by the valve body based upon the
manual lever position, throttle pressure, and gover-
nor pressure. The governor pressure is a variable
pressure input to the valve body and is one of the
signals that a shift is necessary. First through fourth
gear are obtained by selectively applying and releas-
ing the different clutches and bands. Engine power is
thereby routed to the various planetary gear assem-
blies which combine with the overrunning clutch
assemblies to generate the different gear ratios. The
torque converter clutch is hydraulically applied and
is released when fluid is vented from the hydraulic
circuit by the torque converter control (TCC) solenoid
on the valve body. The torque converter clutch is con-
trolled by the Powertrain Control Module (PCM). The
torque converter clutch engages in fourth gear, and
in third gear under various conditions, such as when
the O/D switch is OFF, when the vehicle is cruising
on a level surface after the vehicle has warmed up.
The torque converter clutch will disengage momen-
tarily when an increase in engine load is sensed by
the PCM, such as when the vehicle begins to go
uphill or the throttle pressure is increased. The
torque converter clutch feature increases fuel econ-
omy and reduces the transmission fluid temperature.
Since the overdrive clutch is applied in fourth gear
only and the direct clutch is applied in all ranges
except fourth gear, the transmission operation for
park, neutral, and first through third gear will be
described first. Once these powerflows are described,
the third to fourth shift sequence will be described.
1 - CONVERTER CLUTCH 15 - HOUSING
2 - TORQUE CONVERTER 16 - REAR BEARING
3 - OIL PUMP AND REACTION SHAFT SUPPORT ASSEMBLY 17 - OUTPUT SHAFT
4 - FRONT BAND 18 - SEAL
5 - FRONT CLUTCH 19 - OVERDRIVE OVERRUNNING CLUTCH
6 - DRIVING SHELL 20 - OVERDRIVE PLANETARY GEAR
7 - REAR BAND 21 - DIRECT CLUTCH SPRING
8 - TRANSMISSION OVERRUNNING CLUTCH 22 - OVERDRIVE CLUTCH PISTON
9 - OVERDRIVE UNIT 23 - VALVE BODY ASSEMBLY
10 - PISTON RETAINER 24 - FILTER
11 - OVERDRIVE CLUTCH 25 - FRONT PLANETARY GEAR
12 - DIRECT CLUTCH 26 - REAR CLUTCH
13 - INTERMEDIATE SHAFT 27 - TRANSMISSION
14 - FRONT BEARING 28 - REAR PLANETARY GEAR
Fig. 2 Transmission Part And Serial Number
Location
1 - PART NUMBER
2 - BUILD DATE
3 - SERIAL NUMBER
BR/BEAUTOMATIC TRANSMISSION - 42RE 21 - 137
AUTOMATIC TRANSMISSION - 42RE (Continued)