DODGE RAM 1500 1998 2.G Workshop Manual INSTALLATION
(1) Route the transmission end of the gearshift
cable through the opening in the dash panel (Fig.
72).
(2) Seat the cable grommet into the dash panel
opening.
(3) Snap the cable into the

Page 2079 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (15) Using Spring Compressor 8251, compress the
UD/OD balance piston and remove the snap-ring
from the input clutch hub (Fig. 80).(16) Remove the UD/OD balance piston and piston
return spring from the

Page 2081 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual ASSEMBLY
(1) Install all new seals and o-rings onto the input
shaft and input hub. The o-rings on the input hub
are color coded. Be sure to install the correct o-ring
in the correct location.
(2) Chec

Page 2082 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (7) Install Piston Guides 8504 into the input clutch
retainer (Fig. 83) and onto the input clutch hub to
guide the inner and outer underdrive piston seals
into position.
(8) Install the underdrive pis

Page 2083 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual separator plates can be identified by the lack of the
half-moon cuts in the locating tabs.
(19) Install the overdrive clutch wavy snap-ring
with the two tabbed ears into the input clutch
retainer.
(20

Page 2084 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (24) Install the reverse reaction plate into the
input clutch retainer.
(25) Install the reverse reaction plate selective
snap-ring into the input clutch retainer.
(26) Mount a dial indicator to the a

Page 2085 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (28) Install the number 2 bearing onto the under-
drive hub with outer race against the hub with petro-
leum jelly.
(29) Install the underdrive hub into the input
clutch retainer.
(30) Install the num

Page 2086 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual feedback loop to the TCM. The TCM uses this infor-
mation to adjust its control of the pressure control
solenoid to achieve the desired line pressure.
OPERATION
The TCM calculates the desired line pre

Page 2088 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (5) Remove the overrunning clutch snap-ring (Fig.
94).
(6) Remove the spacer from the overrunning clutch
(Fig. 94).
(7) Separate the inner and outer races of the over-
running clutch (Fig. 94).
(8) Re

Page 2089 of 2627

DODGE RAM 1500 1998 2.G Workshop Manual (13) Measure the low/reverse clutch pack clearance
and adjust as necessary. The correct clutch clearance
is 1.00-1.74 mm (0.039-0.075 in.).
(14) Install the overrunning clutch into the low/re-
verse c