Cylinder head bolt SUZUKI SWIFT 2000 1.G SF310 Service User Guide
[x] Cancel search | Manufacturer: SUZUKI, Model Year: 2000, Model line: SWIFT, Model: SUZUKI SWIFT 2000 1.GPages: 557, PDF Size: 14.35 MB
Page 285 of 557

1. Cylinder head
2. Cylinder head bolt
3. Valve guide
4. Cylinder head gasket:
“TOP” mark provided on
gasket comes to crankshaft
pulley side, facing up
(toward cylinder head side).
5. Pin
6. Camshaft
7. Valve lash adjuster
8. Valve cotters
9. Valve spring retainer
10. Valve spring:
Be sure to position spring in place with
its bottom end (small-pitched) facing the
bottom (valve spring seat side).11. Valve stem seal
12. Valve spring seat
13. Exhaust valve
14. Intake valve
15. Oil seal
16. Gasket
17. Camshaft housing bolt: Tightening Torque
: Do not reuse
: Apply engine oil to sliding
: surfaces of each part.
ENGINE MECHANICAL (G10, 1-CAM 6-VALVES ENGINE) 6A-21
VALVES AND CYLINDER HEAD
INSPECTION
Valve Guides
Using a micrometer and bore gauge, take diameter readings on
valve stems and guides to check stem-to-guide clearance.
Be sure to take reading at more than one place along the length of
each stem and guide.
If clearance exceeds limit, replace valve and valve guide.
Item
StandardLimit
Valve stemIn5.457 – 5.480 mm
(0.2148 – 0.2157 in.)———
diameterEx5.440 – 5.455 mm
(0.2142 – 0.2148 in.)———
Valve guide
I.D.In &
Ex5.500 – 5.512 mm
(0.2165 – 0.2170 in.)———
Stem-to-
guide
In0.020 – 0.055 mm
(0.0008 – 0.0021 in.)0.07 mm
(0.0027 in.)
guide
clearanceEx0.045 – 0.072 mm
(0.0018 – 0.0028 in.)0.09 mm
(0.0035 in.)
Page 291 of 557

1. Cylinder block
2. Front oil seal
3. Main bearing
4. Bearing cap
5. Cap washer
6. Cap bolt
7. Timing pulley key
8. Crankshaft
9. Thrust bearing:
Set oil grooves of bearing to weds.
10. Rear oil seal
11. Pin
12. Oil seal housing gasket
13. Oil seal housing
14. Housing bolt
15. Input shaft bearing
16. Flywheel
17. Flywheel bolt
: Tightening Torque
: Do not reuse
: Apply engine oil to sliding
: surfaces of each part.
78 N.m (7.8 kg-m)
12 N
.m (1.2 kg-m)
ENGINE MECHANICAL (G10, 1-CAM 6-VALVES ENGINE) 6A-27
MAIN BEARINGS, CRANKSHAFT AND CYLINDER BLOCK
REMOVAL
1) Remove engine with transmission from body as previously out-
lined.
2) Remove transmission from engine, and then remove clutch and
flywheel (drive plate for A / T).
3) Remove water pump belt, generator bracket, crankshaft pulley,
timing belt, and crankshaft timing belt pulley etc.
4) Remove cylinder head assembly.
5) Remove oil pan and oil pump strainer.
6) Remove pistons and connecting rods.
7) Remove oil pump and oil seal housing.
8) Remove main bearing caps and crankshaft.
Page 293 of 557

ENGINE MECHANICAL (G10, 1-CAM 6-VALVES ENGINE) 6A-29
5) Install oil seal housing and its gasket.
Install new gasket. Do not reuse gasket removed in disassem-
bly. Oil lip portion of oil seal before installing. Tighten housing
bolts to specification.
After installing oil seal housing, gasket edges might bulge out;
if so, cut them off to make them flush with cylinder block and
oil seal housing.
Tightening Torque
(b): 12 N
.m (1.2 kg-m, 9.0 lb-ft)
6) Install oil pump.
Refer to item “Oil pump” for installation of oil pump.
7) Install flywheel (M / T model) or drive plate (A / T model).
Using special tool, lock flywheel and torque its bolts (1) to spec-
ification.
Special Tool
(A): 09924-17810
Tightening Torque
(c): 78 N
.m (7.8 kg-m, 56.5 lb-ft)
8) Install pistons and connecting rods as previously outlined.
9) Install oil pump strainer and oil pan.
10) Install cylinder head assembly to cylinder block (1).
Before installing cylinder head assembly to cylinder block,
install check valve (2) into oil gallery in cylinder block, directing
slit of valve toward top of cylinder block.
NOTE:
Tighten cylinder head bolts to specified torque as pre-
viously outlined.
Whenever installing cylinder head to new cylinder block,
use following procedure to tighten cylinder head bolts.
Tighten cylinder head bolts to specified torque as pre-
viously outlined and loosen them once till tightening
torque becomes “zero”. And then torque them to specifi-
cation again.
11) Install crankshaft timing belt pulley, timing belt, crankshaft
pulley, water pump pulley, etc., as previously outlined.
12) Install clutch to flywheel (M / T model).
For clutch installation, refer to Section 7C.
13) Install engine with transmission to body as previously outlined.
Page 308 of 557

3
3
ENGINE MECHANICAL (G13B, 1-CAM 16-VALVES ENGINE) 6A1-13
CYLINDER HEAD COVER
REMOVAL
1) Disconnect negative cable at battery.
2) Disconnect breather hose (2) and PCV valve (3) from head cov-
er.
3) Disconnect ignition coil couplers (6).
4) Remove ignition coil assemblies (5) with high-tension cord (4).
5) Remove cylinder head cover (1) with cylinder head cover gasket
and O-rings.
INSTALLATION
1) Install O-rings (3) and cylinder head cover gasket (2) to cylinder
head cover (1).
NOTE:
Be sure to check each of these parts for deterioration or any
damage before installation and replace if found defective.
2) Install cylinder head cover to cylinder head and tighten cover
bolts to specified torque.
Tightening Torque
(a): 11 N
.m (1.1 kg-m, 8.0 lb-ft)
NOTE:
When installing cylinder head cover, use care so that cylin-
der head cover gasket or O-rings will not get out of place or
fall off.
3) Install ignition coil assemblies (5) with high-tension cord (4).
4) Connect ignition coil couplers (6).
5) Connect breather hose (2) and PCV valve (3) to head cover (1).
6) Connect negative cable at battery.
Page 311 of 557

1. Long bolt
2. Short bolt
6A1-16 ENGINE MECHANICAL (G13B, 1-CAM 16-VALVES ENGINE)
10) Remove intake manifold rear stiffener (1) and generator adjust
arm reinforcement (2) from intake manifold (3).
11) Remove intake manifold with throttle body from cylinder head,
and then its gasket.
INSTALLATION
Reverse removal procedure for installation noting the followings.
Use new intake manifold gasket.
When installing intake manifold, install clamps securely.
Tightening Torque
(a): 23 N
.m (2.3 kg-m, 17.0 lb-ft)
Adjust accelerator cable play, referring to Section 6E.
Check to ensure that all removed parts are back in place.
Reinstall any necessary parts which have not been reinstalled.
Refill cooling system referring to Section 6B.
Upon completion of installation, turn ignition switch ON but en-
gine OFF and check for fuel leaks.
Finally, start engine and check for engine coolant leaks.
Page 313 of 557

(b)
(a)
6A1-18 ENGINE MECHANICAL (G13B, 1-CAM 16-VALVES ENGINE)
INSTALLATION
1) Install new gaskets to cylinder head.
2) Install exhaust manifold.
Tighten bolts and nuts to specified torque.
Tightening Torque
(a): 32 N
.m (3.2 kg-m, 23.5 lb-ft)
3) Install exhaust manifold cover(s) (1).
4) Connect oxygen sensor coupler (3) and clamp (2) its wire se-
curely.
5) Tighten exhaust No.1 pipe to manifold nuts and exhaust man-
ifold stiffener bolt.
Tightening Torque
(a): 50 N
.m (5.0 kg-m, 36.5 lb-ft)
(b): 50 N
.m (5.0 kg-m, 36.5 lb-ft)
6) Connect negative cable at battery.
7) Check exhaust system for exhaust gas leakage.
Page 315 of 557

1.“V” mark on cylinder
head cover
2. Timing mark by “E” on
camshaft timing belt pulley
3. Arrow mark on oil
pump case
4. Punch mark on crankshaft
timing belt pulley
4. Tensioner stud
6. Damper
6
6A1-20 ENGINE MECHANICAL (G13B, 1-CAM 16-VALVES ENGINE)
8) Lock crankshaft inserting flat end rod or the like (2) between fly-
wheel ring gear and transmission case, after removing clutch
housing (torque converter housing for A / T) lower plate.
With crankshaft locked, remove crankshaft timing belt pulley
bolt (3).
9) Remove crankshaft pulley bolts (1).
10) Remove crankshaft pulley (4).
11) Install crankshaft timing belt pulley bolt temporarily to turn
crankshaft.
12) Release harness clamps.
13) Remove timing belt outside cover.
14) For installation of timing belt, align 4 timing marks as shown in
figure by turning crankshaft.
15) Remove timing belt tensioner (3), tensioner plate (2), tensioner
spring (5) and timing belt (1).
Page 317 of 557

4. Damper
6A1-22 ENGINE MECHANICAL (G13B, 1-CAM 16-VALVES ENGINE)
2) Install tensioner (2) and tensioner plate (3):
Do not tighten tensioner bolt (1) with wrench yet. Hand tighten
only at this time.
Check to ensure that plate movement in arrow direction as
shown in figure causes tensioner to move in the same direction.
If no associated movement between plate and tensioner occurs,
remove tensioner and plate again and reinsert plate lug into ten-
sioner hole.
3) Check that timing mark (2) on camshaft timing belt pulley is
aligned with “V” mark (1) on cylinder head cover. If not, align two
marks by turning camshaft but be careful not to turn it more than
its allowable turning range which is described on previous page.
4) Check that timing mark (2) on crankshaft timing belt pulley is
aligned with arrow mark (1) on oil pump case. If not, align two
marks by turning crankshaft but be careful not to turn it more
than its allowable turning range which is described on previous
page.
5) Install timing belt and tensioner spring (2).
With two sets of marks aligned and tensioner plate pushed up,
install timing belt on two pulleys in such a way that drive side (1)
of belt is free from any slack.
And then install tensioner spring as shown in figure, and hand-
tighten tensioner stud (3).
NOTE:
When installing timing belt, match arrow mark (
) on
timing belt with rotating direction of crankshaft.
In this state, No. 4 piston is at top dead center of compres-
sion stroke.
Page 328 of 557

1. Camshaft
2. Camshaft oil seal
3. Rocker arm shaft
4. O-ring
5. Rocker shaft bolt
6. Rocker arm (IN)
7. Rocker arm No.1 (EX)
8. Rocker arm No.2 (EX)
9. Valve adjusting screw
10. Valve adjusting screw
11. Clip
12. Lock nut
13. Rocker arm spring
: Tightening Torque : Do not reuse
: Apply engine oil to sliding
: surfaces of each part.
ENGINE MECHANICAL (G13B, 1-CAM 16-VALVES ENGINE) 6A1-33
ROCKER ARMS, ROCKER ARM SHAFT AND CAMSHAFT
REMOVAL
1) Disconnect negative cable at battery.
2) Remove timing belt as previously outlined and remove camshaft
timing belt pulley (1) by using special tool.
Special Tool
(A): 09917-68221
3) Remove cylinder head cover as previously outlined.
Page 329 of 557

1. Oil plug
6A1-34 ENGINE MECHANICAL (G13B, 1-CAM 16-VALVES ENGINE)
4) Disconnect CMP sensor coupler from CMP sensor.
5) Remove CMP sensor case (1) from cylinder head.
Place a container or rag under CMP sensor case, for a small
amount of oil flows out during removal of case.
6) After loosening all valve adjusting screw lock nuts (2), turn ad-
justing screws (1) back all the way to allow all rocker arms (3) to
move freely.
7) Remove camshaft housing and camshaft.
NOTE:
To remove camshaft housing bolts, loosen them in such or-
der as indicated in figure, a little at a time.
8) Remove timing belt inside cover (2).
9) Remove intake rocker arm (1) with clip (2) from rocker arm shaft
(3).
NOTE:
Do not bend clip when removing intake rocker arm.